96 South Main Street, PO Box 77, Nephi, Utah 84648 - Voice: 435 623-0525 - FAX: 435 623-4735

On our front page this week

  • Mona may be required to monitor water for arsenic



By Myrna Trauntvein
Times-News Correspondent

The Environmental Protection Agency may require Mona to monitor the culinary water system for arsenic.

"So far, Mona's source is not a concern for arsenic," said Doran Kay, council member. "The EPA has a list of some of the towns that need to be concerned about arsenic in their drinking water and Mona does not appear on the list anywhere."

When the new well begins to produce and that water is part of the system, he said, the town may be required to begin that monitoring program.

"When we start operating the well, we will be pulling underground water into our system. Perhaps then we will be subject to arsenic monitoring."

All of the new and stricter requirements being imposed on culinary water systems throughout the state had a price tag. "All of these types of monitoring and sampling are going to cost us some money," he said.

Monitoring may cost the town more than $2,000 per quarter.

•Mona Town Council members agreed to authorize the issuance of a water revenue bond, series 2000, and adopt a bond resolution authorizing the issuance of the bond.

Doran Kay, council member responsible for the water system, received word from bond counsel, Ken Chamberlain, Chamberlain Associates, LLC, that the resolution should be on the agenda for Tuesday evening.

"We will be borrowing an extra $100,000," said Kay. "The amount will roll over and will add five years to the repayment plan."

There will be a $51,000 payment each year, he said. The payment amount has not changed but will extend to 25 years instead of the 20 years originally set for the first bond. That bond was used for development of the new well drilled and put into service this past year.

The council is tentatively planning to hold a hearing for the issuance of the bonds during the first week of November.

"The Utah State Division of Drinking Water has agreed to the plan as we presented," said Kay.

The extra money is needed, he said, to complete the water project. The project is going over budget even though some parts of the project were trimmed after the first bond was awarded.

"The project is also being more expensive than what the engineers had projected. They projected it to be a $686,000 project," said Kay. "We (council members) thought, perhaps, we could take $50,000 out of the town cash flow to finalize the project and not have to finance any of it. However, that's not going to happen anymore."

Included in the new amount is $10,000. The money is projected for expenses the town may incur in discovering what problems the water line under the freeway has and, if needed, to pay for enlarging the line.

"All phases of the project have been completed to date except the pump station for the well," said Kay. "The amount of money that was approved for the project has been used and Mona is in need of additional funding assistance to finish this last phase of the project."

Kay said the previous application the town had submitted was recent enough that another application did not need to be done. An addendum was added to the previous application.

"Extending the term of our loan from 20 years to 25 years will allow us to manage our cash flow within our existing budget," he said.

•The low bidder on the final phase of the culinary storage system wants to work with Mona so the project can be completed with a protective structure built to house the expensive electrical equipment used at the well.

K&P Plumbing, Orem, entered the low bid of $76,000 to install the pumping equipment and the needed valves for the water project.

"Steve Kay, of K&P Plumbing, said he was concerned about the $12,000 worth of switches we have," said Doran Kay, council member responsible for the water project. "They will be on a steel rack inside a steel box, but they could be damaged by a gunshot."

Steve Kay said he would be willing to go ahead and erect a protective building of concrete block and then accept the pay for the construction July 2001.

A building was part of the original plan for the water project but was scrapped for lack of funds.

"The $76,000 bid includes equipping the well with a submersible pump and a transducer. A transducer will act as a safety precaution for the submersible pump in the event that the water level in the well drops below the water pump."

A pump control valve will be needed and, like the transducer, will require a change order, said Kay, unless another method of funding it can be found so that it will not have to be part of the change order which would cost the town more money.

"There's a possibility we can have the Rural Water Users help us with that particular device. Maybe it would be cheaper for Mona to go that route," said Kay.

"If he (Steve Kay) is willing to construct the building now and take pay later, I think we should go ahead and complete the project," said Bryce Lynn, mayor.