  • Bid of $256,500 for first phase of construction at Nephi City Airport is authorized


By Myrna Trauntvein
Times-News Correspondent

A contract with the engineering firm of Cramer and Noble was approved at Tuesday's Nephi City council meeting.

The council also authorized the mayor to sign the contract for engineering services for the first phase of construction at Nephi City Airport.

"All phases are completed except for the construction phase," said Randy McKnight, city administrator. "The project has been broken into phases because of federal funding requirements."

The first phase will consist of grading the runway, establishing and providing electrical service for lighting, and the constructing the perimeter fencing.

"The city must contract for each phase," said McKnight.

He said that, in the next three weeks, bids would be announced for the coming work.

"Cramer and Noble will make a recommendation for who to award the bids and will make certain the bids answer federal regulations as well as sticking to cost restrictions," said McKnight.