96 South Main Street, PO Box 77, Nephi, Utah 84648 - Voice: 435 623-0525 - FAX: 435 623-4735

On our front page this week

  • PacifiCorp hearings postponed until February


By Myrna Trauntvein
Times-News Correspondent

It may be as late as February before an order from the Utah Public Service Commission is made as to whether or not to allow construction of a power plant near Mona.

PacifiCorp had hoped to start construction in January on a $350 million power plan in Juab County.

The company originally helped for a Dec. 31 approval date so construction on the first phase of the 525-megawatt natural-gas fired plant, known as the Currant Creek power project, could begin by Jan. 15.

Robert A. Van Engelenhoven, P.C., Manger of Resource Development with PacifiCorp said the power company hoped to receive the go-ahead to begin construction so the plant could be on-line by the summer of 2005.

"We plan to build the plant in phases," he said. "We want the first phase built by June 2005 and plan to continue construction to complete the project until March 2006."

If the plant did not come into being soon enough, rolling blackouts along the Wasatch Front could occur, he said.

PacifiCorp had been working toward hearings to be held toward the end of Jan. 2004. Now those hearing dates have been postponed until mid-February.

Nevertheless, Bill Landels, PacifiCorp executive vice president, said after meeting on Tuesday with the commission that the approved hearing dates of Feb. 18-19 were workable.

"I think we've got to come out of this process with all parties feeling due process was done and seen to be done," said Landels.

Some of those allowed to bid on the power project are dissatisfied with PacifiCorp's bid process and have complained.

The company rejected 28 proposals submitted by 13 outside companies and, eventually, awarded itself the contract to build the plant.

Van Engelenhoven said the company's bid was $320 million less expensive than the next-best cost alternative when evaluated over a 20- to 30-year life span of the proposed plant.

PacifiCorp's hired consultant, Navigant Consulting Inc., had concluded that the company's open bid process was conducted in a fair manner, said John Eriksson, an attorney for PacifiCorp.

"Navigant spent hundreds of hours evaluating the company's process, working with bidders in evaluating bids, determining just what the bid terms were," Eriksson said. "So having gone through all that work, now we find ourselves facing claims or parties taking issue, it seems, with the process itself."

The first phase of construction would be developmental, with the site being cleared and readied. Temporary facilities, such as an office for construction management would be placed as would other small buildings.

Work would be done on the well and the laying of water lines from the well site east of Mona near I-15 to the plant site west of Mona.

A work force peak of 300 workers was expected during the summer of 2004. Then the work force would taper and would peak again in 2005.

"We have planned a very aggressive construction goal," said Van Engelenhoven.

How the postponement of the desired hearing dates will affect the hoped for construction completion goal remains to be seen.

In addition, some of the complaints levied against PacifiCorp by disgruntled bidders who are questioning the company's award of the bid to themselves may slow the construction more, depending on the outcome.