96 South Main Street, PO Box 77, Nephi, Utah 84648 - Voice: 435 623-0525 - FAX: 435 623-4735

On our front page this week

 

  • Mona City may have to step in and call a default on bond between developer and contractor


By Myrna Trauntvein
Times-News Correspondent

Mona continues to be in the middle on a dispute between a developer and a contractor even though they do no want to be involved.

George Johansen sent a letter to the city to inform them that he was going to choose the option of going to court in the dispute between Lyn Bonner and himself as to contracted work done and not paid for.

Bonner and Jason Ivans told council members that they had been trying to work with Johansen on the problem but had been unable to meet with him.

"We can stop building permits until you solve the problem," said Mayor Bryce Lynn.

"We offered to pay one-half of the amount if he should reduce the lean by that much but he rejected our offer," said Bonner.

Quinton Kay, council member, said he had offered the city office as a meeting place for the two (Bonner and Johansen and their attorneys) to meet. He thought a meeting had been slated for May 31 but it did not transpire.

Ivans, manager of the subdivision project and a partner in O'Sullivan Investment LC, said he could not meet with Johansen on May 31 because his partner was out of town and because he was not even notified of meeting by the Johansen company until the day before the meeting was proposed.

The bond guaranteeing the project was signed in July and it is due to expire in 18 months from the signing date. In addition, said Kay, the city may have to step in and call a default on the bond.

"You are just nip and tuck on the bond," said Kay.

He showed Bonner and Ivans a list on items still to be paid for by the company. If the city had to pay the debts owed by using the bond, said Kay, there may not even be enough to do so.

The bond amount remaining was $181,000,

The money still to be paid out included a read rebuild on 700 South which would cost $20,000 and the several thousand dollars Johansen has billed.

There is also an outstanding bill of $95,000 to Staker Paving for work done on the project.

"That bill is closer to $80,000 and should be resolved soon," said Ivans.

He said the company was working with the Bank of American Fork and would make certain there was enough in the bond to cover expenses in case of default.

However, he said, he had met with Staker Paving and that bill would soon be paid and that amount would still be in the bond so that, he said, should relieve some of the concern.

"We will comply with the city ordinance," he said.

Ivans, also an attorney, said he would go to court in defense of the stand taken in the Johansen dispute. All O'Sullivan wanted was for a detailed billing to be submitted by Johansen because some amounts charged were in question.

"We will go to court if we have to," Ivans said.

Before a bond can be released, said Kay, the subdivision has to be accepted. If there is still work to be done and items to be repaired or replaced, the bond will not be released until the work is done.

"The bond needs to cover 20 percent of the residual as a hold over," said Kay.

Ivans said that his company had been trying to meet with Johansen.

"For the first four months, they just blew us off," he said.

"You agreed that we (the city) would set up a meeting with both of you," said Harry Newell, council member.

The city had done its part but the meeting had not taken place.

The letter the city had received, said Lynn, indicated that meeting time was over and that Johansen had made the decision to let the courts decide what was right and wrong between the two disputers.