96 South Main Street, PO Box 77, Nephi, Utah 84648 - Voice: 435 623-0525 - FAX: 435 623-4735

On our front page this week

  • Currant Creek begins generating power; will not seek additional tax breaks; promises to be environmentally friendly


PLANT TOUR • John Bowater, plant manager, explains plant operation to Deseret News writer Dave Anderton.as David Eskelsen, PacifiCorp/Utah Power spokesman listens. The plant, while still under construction, began generation of power. The plant should be completed in 2006.

By Myrna Trauntvein
Times-News Correspondent

It is, very much, still a construction site but the Currant Creek power plant began generating electricity this week for the first time.

In addition, the long awaited power generation will mean a larger tax base for Juab County and will bring some dollars to the table for needed projects.

"We have not applied for a tax break," said Robert A. Van Engelenhoven, P.E., Manager of Resource Development for PacifiCorp.

He said that did not seem right, to ask an area to welcome them and then take part of that joy away. PacifiCorp will pay the fair tax on its holdings which will be good news to county residents.

To celebrate the first power generation at the facility, members of the press were invited to meet in the new office building and take a walking tour of the plant site which has begun its life supplying enough power to light up approximately 144,000 homes.

"This week, on June 20, we were called on to begin producing power," said John Bowater, plant manager.

The plant is operating as a single cycle producer of power for the high demand summer months. That will change at the end of summer.

 On-hand for the tour were Bowater; David Eskelsen, Corporate Communications, PacifiCorp/Utah Power, Utah Power's parent company; and Van Engelenhoven.

Since more Utahns are switching to central air conditioning and more homes are being built all along the Wasatch Front, electrical demand is increasing by leaps and bounds.

In fact, peak electrical demand is increasing by 5.4 percent each year and base demand is rising at 2.6 percent annually.

"The summer operation will continue through to October," said Bowater. "Then the plant will shut down and the 280 megawatt simple cycle will be converted to the 525 megawatt combined cycle."

The plant will then be ready to go back on line with full capacity by April 2006.

"The one thing that's really great about this plant is the flexibility options in providing power to customers," said Bowater. "On those high-demand days, the plant can respond quickly."

The summer production rate Current Creek is providing gives the extra power needed to prevent summer brown-outs (where the lights get dim) and outages.

But once it is finished and on-line, the combined cycle will generate 420 megawatts. The duct firing mechanism being constructed will add additional peaking capability of 105 megawatts.

At full capacity, the natural gas fired combined cycle project will produce electricity with two gas turbines, two heat recovery steam generators and one steam turbine.

The completed plant will be connected to the 345 kV transmission backbone at Mona.Most of that generation will find its way to Utah Power customers along the Wasatch Front.

Eskelsen said the staff in commerce and trading located at PacifiCorp's Portland office determines the amount of power to be generated and just where in the power grid system that power will be directed.

The office then dispatches the order of how much power needs to be generated.

"That changes from hour to hour and day to day," said Bowater.

The changes come because the system is economically driven.

"We run on market economics," he said.

The $350 million Currant Creek power plant is the first of three natural gas-fired plants planned for Utah over the next four years.

There are two 80-foot stacks,

The plant employs 24 people full time. Two men work in the control center around the clock on shifts of 12-hours each.

There are approximately 400 construction workers still on site but that number will continue to dwindle as the work on the second phase winds down.

When completed, the plant will provide enough power for nearly 270,000 homes.

Currant Creek is the first significant power plant over 300 megawatts to be built since 1983, when the Hunter power plant's third unit became operational, said Eskelsen.

"The growth in electricity consumption demand in Utah is just enormous," Bowater said. "Five percent growth is the sign of a very healthy economy. I've never seen so much home-building going on."

Operating at full capacity, Currant Creek will consume 90,000 decatherms of natural gas per day. The gas supply will come from a 13-mile line connected to Questar.

"Both Questar and Kern River lines are high pressure gas transmission pipelines with 1075 psi," said Bowater.

Another bit of good news for local residents is that the natural gas fuel used at the plant means that the air quality will not be compromised in any way. Unlike coal-fired power plants, the Currant Creek plant does not need scrubbers.

In addition, the water which has been recycled finally ends up in the evaporation pond. That water is also extremely pure water as is the steam made from the water in the first place.

"Currant Creek is quiet," said Bowater.

He pointed out that the plant had started up at 11 a.m. while reporters were in the control room and there was no loud noise to call attention to the fact that the plant was again on-line for the day.

The plant is not on all of the time. It comes on line, presently, just for the peak use hours of the day.

One thing he was proud of, said Bowater, was that over 1.0 million man hours have been worked to date with a peak of 400 construction staff on site at one time.

"Safety has been important to us," he said. "We have no lost time accidents and only five recordable incidents. That is a safety record eight times better than the Utah average and six times better than the national average for construction projects."

PacifiCorp has commissioned a second power plant, which is under construction at the former Geneva Steel site in Vineyard. The utility will be soliciting bids for a third power plant this summer.

"Our resource planning has indicated that there'll be a substantial need for this kind of investment to serve the growing demand for electricity," Eskelsen said.