96 South Main Street, PO Box 77, Nephi, Utah 84648 - Voice: 435 623-0525 - FAX: 435 623-4735

On our front page this week

  • Spring Canyon Energy LLC gets go-ahead to negotiate contract with PacifiCorp


By Myrna Trauntvein
Times-News Correspondent

Juab County Commissioners expressed excitement over a recent order by the Utah Public Service Commission which made it possible for a Texas company to build a $200 million natural gas-fired power plant near Mona.

They are most excited about the possibly leading to the creation of 100 new jobs.

Dallas-based Spring Canyon Energy LLC was given the go-ahead by the Utah Public Service Commission to negotiate a contract with Portland-based PacifiCorp for 100 megawatts of electricity under a so-called "qualifying facility" provision that requires utilities to purchase excess electricity generated.

A megawatt is enough power to provide electricity to roughly 500 to 700 homes.

"I was present at the Utah Public Service Commission meeting," said Robert Steele, commissioner. "This is a totally different project than the Current Creek Power Plant."

This plant would be known as the Spring Canyon Power Plant, said Steele. It is named after Mona's Spring Canyon.

Increased demand for electricity has put the state on the verge of an energy crunch. Co-generation facilities, like Spring Canyon's, would help meet high demand.

Doug Larson, PacifiCorp's vice president of regulatory affairs, said Utah's peak demand is growing at 5.4 percent annually. Because of that growth, the state needs roughly 250 megawatts of additional capacity each year.

Steele said the ethanol plant is an off-shoot of the steam produced by the plant. Utilizing the steam for the plant to make ethanol is a great idea, he said.

Electricity from the co-generation power plant would be sold to PacifiCorp, which operates in Utah as Utah Power, at a price of $50 to $60 per megawatt. The plant's steam would be sold to an industrial customer to make ethanol.

Neil Cook, chairman of the Juab County Commission, said the commission is excited about the addition of another power facility and welcomes the power plant and jobs it will bring to a county with just 9,500 people.

"Juab County is a very poor county," Cook said.

He said the jobs generated would be more than welcome. In addition, he said, it would be wonderful to have the increased property tax base. The increase in taxes would help generate the money needed for many services.

"Our tax base has been stagnant for a long time. This power plant would increase our tax base and therefore help our schools, help our roads, help everything that we do as a county to provide the necessary services to the citizens."

Val Jones, commissioner, said he joined the others in being pleased to have the company build in Juab County. In addition to the increase in jobs and the tax base, the construction phase was also a help to the local economy.

Several companies competed to secure permission to build a plant, including Pioneer Ridge LLC and Mountain Wind LLC, which intended to build two wind parks that would generate 48 megawatts of electricity.

In addition, ExxonMobil Production Co. had petitioned the Utah commission to approve the sale of 75 megawatts of power from a qualifying facility it owns near Kemmerer, Wyoming. The Division of Public Utilities had recommended that ExxonMobil be awarded the 100 megawatts.

"The plant would need to be built in a hurry," said Cook. "It would need to be on-line by 2007."

Spring Canyon is required to complete its facility by June 1, 2007. Cook said he thinks that is not enough time, since Spring Canyon must reach a contract with PacifiCorp before building the facility.

"I still don't look at it as a done deal," Cook said. "I don't see any way in the world they could be on-line by June 2007 without getting some kind of extension."

In his opinion, after attending the meeting, said Steele, he was optimistic. "It looks very favorable and looks like it will be built in our county."

Steve Mecham, an attorney for Spring Canyon, said he did not anticipate any road blocks in striking a contract.

"The (PSC) commission," Mecham said, "while ordering that Spring Canyon was first in line for those remaining 100 megawatts, also ordered good faith negotiations, and that's what I expect of both parties."

Steele said he also considered the good-faith negotiations to be of benefit to getting the plant in service in short-order.

Dave Eskelsen, a spokesman for PacifiCorp, said past qualifying facility contracts have taken two to three months to negotiate. Spring Canyon has estimated it will take 18 to 24 months to build the plant.

Larson questioned whether 100 megawatts will be enough to make Spring Canyon's plant economically viable.

"There are economies of scale," Larson said. "My guess is that the reality of a 100-megawatt plant being the best and most economical is not there. It probably takes a larger plant than that."

PacifiCorp already is constructing a $350 million natural gas-fired power plant near Mona. The 525-megawatt plant, called the Currant Creek power project, will be completed in two phases, with 280 megawatts operational by the summer of 2005 and 245 megawatts in 2006.

The stack for the project is currently being erected and Eskelsen said the plant was on schedule for the expected opening. Construction was going as planned, he said.

"A gentleman from a magnesium plant was at the public service commission meeting," said Steele. "He read the state statutes to us which explained what the state requires. It was most helpful to us."