96 South Main Street, PO Box 77, Nephi, Utah 84648 - Voice: 435 623-0525 - FAX: 435 623-4735

On our front page this week

  • Nephi City water project plans to deliver more water to the storage tanks and to the irrigation pond


By Myrna Trauntvein
Times-News Correspondent

On Monday, June 17, an approximately $500,000 Nephi City water project began digging with a single crew.

The crew began work necessary to place a 16-inch water line under the freeway overpass at 700 North.

"The contractor for this construction work is Claw Construction, Inc. from Wales," said Randy McKnight, city administrator.

McKnight said property owners along the route had been sent a letter informing them of the project and of its scope.

The line will be constructed on the west side of 300 West from 200 North to 600 North, on the north side of 600 North from 300 West to 900 East, on the west side of 900 East from 600 North to 700 North, and on 700 North from 900 East to the blue storage tank and the irrigation pond east of Nephi.

"The purpose of the construction project is to be able to deliver more water to the storage tanks and to the irrigation pond and our objective is to complete the project as soon as possible," McKnight said.

Water from a city-owned well at the street department equipment shed at 200 North and 300 West will be placed in the new pipeline. The well, once used to place water directly into the water delivery system at the site, has not be used for some time.

"The well will be used to provide backup for our basic supply that comes from springs," McKnight said.

In addition to the springs, the Jones well has been the major supply of water during the heat of summer when the springs, by themselves, no longer provide an adequate amount to keep the storage tank at capacity.

It is not that the supply from the springs decreases at this time, in fact, water from those sources actually increases with the warm weather, said McKnight. But the increased demand makes it so that additional water is needed to meet the needs of outdoor watering.

There has been no backup for the Jones well, said McKnight. That has been a concern to the city council.

If anything were to happen to make it necessary to repair the pump, for example, water for fire protection and other uses which take an inordinate amount would suffer.

"There will, ultimately, be three crews working on the project," said McKnight. They will work in tandem to get the project finished so the water from the well can be used this season.

"The contractor will work to minimize inconvenience to property owners along the route and to vehicle and pedestrian traffic."

However, there will be, as with all construction projects of this magnitude, a certain degree of inconvenience, noise, dust and mud.

"Large trucks and heavy equipment will be used on the project," said McKnight. "We are asking that those who have small and curious children remind them to stay clear of the construction zone."

Some of the restoration work will follow the installation of the water line and its initial operation and testing, said McKnight.