96 South Main Street, PO Box 77, Nephi, Utah 84648 - Voice: 435 623-0525 - FAX: 435 623-4735

On our front page this week

 

  • New power plant will bring upgrade in power lines in Mona


By Myrna Trauntvein
Times-News Correspondent

Mona may benefit from the construction of a power plant near the community in that the need increase in capacity power lines will bring a needed up-grade to the community."

At a meeting held with local government officials, members of Utah Power and PacifiCorp told those in attendance that the power upgrade was going to be required.

"A new overhead line, consisting of bigger and heavier wire, will be required to meet the needs of PacifiCorp," said Merrill Brimhall, a Utah Power representative.

In fact, Lee Taylor, Supervisor D&T and Electric Operations for Utah Power, said he had already received a change out order.

"If the change were not made, the city would soon be out of capacity," said Brimhall.

The growth which has occurred in Mona in recent years has pushed the delivery of power to the limits. However, in spite of community official requests, the power was not on a high priority up-date list.

Now it is.

In addition, a transformer and reconductor, which are at or near capacity, will be changed out.

"We will also build line out to our plant," said Brimhall.

In addition, some new poles, some pole bracing, and other safety issues will be considered.

The Current Creek project must still receive regulatory approval from the Utah Public Service Commission. In addition, air quality permits must be obtained and approval for a transfer of water source must be obtained.

On Monday, concerned parities who are questioning the bidding process, met with PacifiCorp representatives and a host of regulatory advisors in a nearly four-hour Utah Public Service Commission technical conference to review the bid process.

The Current Creek Project calls for the new plant to be located next to the Mona substation, a major transmission interconnection point.

The new power generation plant location lies within a group of interconnected transmission substations that serve the Wasatch Front.

This is the first project under a new resource plan by the company to provide 4,000 megawatts of new electricity to its six-state region. Much of the future generation will used in Utah.

The company is pressing the Utah Public Service Commission for regulatory approval by Dec. 31 which would result in first-phase operation by June 2005.

  The 525-megawatt plant will be completed in two phases, with 280 megawatts operational by the summer of 2005 and 245 megawatts in 2006.