96 South Main Street, PO Box 77, Nephi, Utah 84648 - Voice: 435 623-0525 - FAX: 435 623-4735

On our front page this week


  • Commission hears facilities at Mona Reservoir are nearly complete


By Myrna Trauntvein
Times-News Correspondent

The Juab County Boating Facilities Park at Mona Reservoir are nearly complete and the project should be finished within the next two weeks.

Mike Seely, county administrator, said most of the work was done, or nearly so, and it would not be a problem to finish the project if all the work was done on schedule.

"The concrete boat ramp is poured and rip-rap has been placed," said Seely. "The concrete sidewalks have been completed, and the fire rims have been placed and concrete poured around them."

The sites for the picnic tables have been prepared and are ready for the tables to be installed.

"The parking area is compacted and is ready to asphalt," said Seely.

The project was approved for funding by the Utah Division of Parks and Recreation and the Utah Division of Wildlife Resources in February of this year.

"Our grant application requested a total of $90,000 for the construction of a sanitary public toilet, a concrete motorboat access ramp, and a parking area with asphalt paving, a courtesy dock, fire rings, picnic tables and trash receptacles replacement," said Seely.

Of the total amount requested, he said, the Wallop-Breaux Motorboat Access fund contributed $67,500 with another $11,250 provided by the Utah Division of Parks and Recreation.

Juab County provided equipment, manpower and road base equivalent to $11,250 as their share of the project.

"Due to the number of proposed projects and the limited funds available, we were not able to receive the funds for the access road improvements," said Seely.

The county can apply for the funds for that part of the project again this fall to be considered for 2001.