96 South Main Street, PO Box 77, Nephi, Utah 84648 - Voice: 435 623-0525 - FAX: 435 623-4735

On our front page this week

  • Mona City Council sets priorities on water projects


By Myrna Trauntvein
Times-News Correspondent

Three water projects need to be prioritized and considered by the city council for the near future.

The projects were the most important of several water issues discussed by the council at their bi-monthly meeting on Tuesday.

"We need to pick the most crucial item on the list and do it this year," said Doran Kay, council member. "The other projects need to be addressed as we can do them."

Kay said, to his way of thinking, the water line under Interstate-15 was the most important. However, following closely in priority, would be lining the old culinary water tank so that it would no longer leak and developing Large Vest Spring to be used for culinary water.

"I think we need to plan on the water line under the freeway as the most important of the projects and complete that this year," said Bryce Lynn, mayor.

Kay said the estimated cost to have K & P Plumbing replace the water line running under the freeway, according to Steve Kay, would be approximately $20,000.

"Steve Kay recommended using HCPE pipe which would be 10-inch or 12-inch field fused," said Kay. "He estimated the cost to be $6,000 to $8,000 and labor costs to be $6,000 to $8,000."

The rest of the money estimated as needed for the project would be used if needed for cost overages which might occur as the project is completed.

To prevent the whole city from being without culinary water service for three to four days during the replacement project, it was suggested a four-inch temporary by-pass line be run over the freeway overpass at Cemetery Lane.

Allen Pay, water master, also was concerned about inspections being done on water lines installed in developments. New water lines are being charged, for example, in the George Smith development without Pay's authorization.

"George Smith charged the line himself and did a chlorination sweep," said Bryce Lynn, Mona mayor.

Ludlow Engineering, retained as the city engineering firm, makes certain the water line is laid correctly before any line is charged. However, Pay wants to make it clear that he has to give his permission before a line can be charged.

Pay also wanted the council to establish a rate for drawing water out of a fire hydrant for construction use.

"George Smith is drawing unauthorized water from a fire hydrant to spray the construction area for dust control," said Kay. "It has been recommended that the city purchase a two-inch meter with a gate valve. The meter could then be rented out to developers."

A relay switch burned out in the automatic switch that controls the waste valve on the new well. It had to be replaced by an electrician.

"I would like to have the cemetery water metered," said Pay. "Once that is done, all the major water users would be metered."

In order to determine the usage of culinary water, said Pay, the actual use of water needs to be measured.

The new park, the Sand Hills Park, will be watered with the secondary system.

Pay said that a water pipe located on 200 East froze last winter.

A representative of the rural water department used a mine sweeper, the kind used to locate bombs and land mines underground, to find the valves.

Pay also rebuilt a six-inch bladder valve used to fill the lower tank.

In addition, he said, the irrigation pond is now on line.

"The irrigation pond is the one (of two bordering the freeway on the east) closest to the freeway," said Pay.