96 South Main Street, PO Box 77, Nephi, Utah 84648 - Voice: 435 623-0525 - FAX: 435 623-4735

On our front page this week

  • Pacificorp defends bidding process in public hearings


By Myrna Trauntvein
Times-News Correspondent

Friday was the third day of a Utah Public Service Commission hearing on the PacifiCorp's application to build a power generation plant near Mona that would be ready by the summer of 2005.

PacifiCorp operates as Utah Power in Utah and Idaho and officials of the company have claimed the plant is needed to help meet escalating power needs.

Called the Currant Creek project, the mega-generation plant has come up against a hard wall in dealing with losing bidders for the project.

Those bidders have charged the utility's "self-build" decision was made before the company completed a review of more than 100 power-supply bids. and that the company had a conflict of interest as both a bidder and bid selector.

"The question can be asked, 'Was the RFP (request for proposals) process perfect?' I'll tell you right now it wasn't," testified Doug Larson, PacifiCorp vice president of regulatory affairs.

The gas-fired Currant Creek plant will cost $345 million to construct as planned with the bid used which was accepted. Officials testified they think that figure is $320 million less expensive, over the life of the plant, than the next-best bid.

A PacifiCorp official testified Friday that the bidding process to get proposals on future power supplies, while imperfect, was nonetheless fair.

In response to a question from Commissioner Constance White, Larson said in the future bid processes could have better communication elements.

In a series of questions from Steve Mecham, an attorney for losing bidder Spring Canyon Energy LLC, Larson acknowledged that he had no detailed involvement in the bidding process but said that those interested in bidding were made aware of the utility's future power needs, the bidding process, and the company's plans to hire a third-party consultant to provide fairness for the process.

The company-hired consultant, Navigant Consulting Inc., determined PacifiCorp's "self-build" choice was best, although other bidders do not agree.

"PacifiCorp treated each bid and bidder consistently and fairly," Navigant principal Howard Friedman said Friday. PacifiCorp so far has paid Navigant $450,000 for its work.

The hearings will continue Wednesday.

At commission chairman Ric Campbell's suggestion, PacifiCorp will provide more details about the economic impacts to customers in 2005 and 2006 if the Currant Creek project is not built.

Rand Thurgood, PacifiCorp's managing director of resource development, testified that in order to meet 2005 summer load demand, Currant Creek was the only way to go forward.

He said the utility has spent about $10 million on the project so far and calling it off would cost $36 million more by month's end, primary to terminate orders for large-scale equipment.

The figure would reach $126 million in loss if the plant were a no-go four months from now.