96 South Main Street, PO Box 77, Nephi, Utah 84648 - Voice: 435 623-0525 - FAX: 435 623-4735

On our front page this week

 

  • Hearings for Pacificorp Current Creek power plant to begin next week


By Myrna Trauntvein
Times-News Correspondent

Hearings on the Currant Creek plant are scheduled to begin next week.

Those hearings mean the plan to build a 525-megawatt, natural gas fired plant near Mona still have a few snags to overcome in the hearing process.

In addition to the hearings, proposed legislation governing competitive bidding procedures for electric generation in the state is being considered by the legislature.

PacifiCorp chose itself last November to build the nearly $350 million power plant, called the Currant Creek project, from among 79 individual bids.

The power plant must still receive regulatory approval from the Utah Public Service Commission before it can actually be built.

Sen. Curt Bramble, R-Provo has introduced, SB198, granting rule making authority to the Public Service Commission in establishing new parameters for competitive bidding on electric generation.

"Right now all the utility has to do is consider other proposals, and once they've considered them, then they can make whatever selection they want," Bramble said.

He said current regulations don't require the utility to require choose the lowest cost provider.

The most important condition among the new rules would be an independent evaluator.

That evaluator would be chosen by the Public Service Commission to oversee competitive bidding against a utility self-build option.

For the Currant Creek process, the outside evaluator was chosen by PacifiCorp.

Prevailing rules are such that utilities only make a return based on their capital investment. The new bill builds in an incentive mechanism, allowing the utility a rate of return on power purchase contracts.

PacifiCorp operates as Utah Power in Utah.

The utility opposes the bill.

"It would effectively force Utah Power out of the power plant building business," said Dave Eskelsen, a spokesman for Utah Power.

Bramble disagreed. He said, under the current system, a utility has no incentive to select an outside bidder.

"They're the ones that have to build the power plants, because that's where they get the return for their shareholders," said Bramble.

Considering the shareholder did not mean Utah taxpayers or Utah ratepayers would receive either the lowest cost or the best options.

PacifiCorp maintains its self-build option for Currant Creek was $320 million less expensive (over the life of the plant) than the next-best cost alternative bid it received.

"We believe that our process was eminently fair and that Currant Creek was selected because it was the lowest cost option and best value for customers," Eskelsen said.