96 South Main Street, PO Box 77, Nephi, Utah 84648 - Voice: 435 623-0525 - FAX: 435 623-4735

On our front page this week

  • Thirteen miles of I-15 will be reconstructed later this year


By Myrna Trauntvein
Times-News Correspondent

A 13-mile stretch of freeway in Juab County. From Sevier River Northward, will be reconstructed this year.

The project has been tagged at $22 million which comes, mostly, from Federal Highway dollars.

Two officials from the Utah Department of Transportation met with the Nephi City Council to inform council members of the re-surfacing and re-compacting of Interstate-15 near Yuba Dam.

Brent Schvaneveldt, project manager, and Geoff Dupaix, public involvement coordinator, representing UDOT, said the project would begin this Spring. Work is tentatively scheduled to begin in April and end in October.

"UDOT originally completed constructing I-15 south of Nephi in 1984," said Dupaix. "The pavement worked well for many years, but recently, the concrete pavement began to sink in various locations along the freeway."

The highway work became essential because of the concrete pavement settling deeper than was anticipated. Construction crews will "rubbelize" the existing concrete surface.

"This means the concrete will be broken up into small pieces and used for road base," said Dupaix. "Additional roadbase material will be added, then paved over with asphalt."

The addition of the roadbase should help even out the ride, he said.

"One mile of the road is built over collapsible soil and another one-mile area is built in a place where the soil expands," said Schvaneveldt. "Because we will see some movement in the future, concrete will not provide the answer we need. Asphalt will be easier to maintain ."

"Asphalt is more flexible," he said.

Water drainage will also be addressed as the road is reconstructed.

Trucking companies which use the road quite heavily should be notified in advance of the summer work and the slower traffic which will result. UDOT officials will appreciate the assistance of city and county officials in identifying those companies so they can be notified in advance.

The rough ride, he said, makes the road dangerous and unsafe for travelers and the repair is needed to increase public safety.

Motorists and truck drivers using the freeway between Nephi and the Juab/Millard County line notice a rough and bouncy ride along sections of the freeway. The rough ride is caused, he said, by the sinking sections of concrete.

"We also plan to create more height clearance under the bridge at the turn-off to Yuba Lake," said Dupaix. It is a tight fit for semi-trucks as it is presently constructed.

He said the bridge would not be raised, rather the road going under it would be excavated. After it is made deeper, it should create the needed clearance for tractor-trailer unites to better utilize the underpass.

The freeway will be begin near milepost 199 near Yuba Lake junction, and will extend northward ending at milepost 212.

"Sections of the road will be closed during construction," said Dupaix. "Traffic will be detoured across the median, restricting motorists to one lane in each direction."

Schvaneveldt said a slurry mix was not the answer to stabilizing the roadbase. It is good to use around utilities but is too expensive for roadbase.

"There will still be concrete roads," said Dupaix. "It is good for areas like Salt Lake City and provides a long-term surface with less maintenance."

However, where the soil is unstable, as it is south of Nephi, asphalt is a better solution because sections of it can be resurfaced. Concrete slabs just sink and make the ride uneven.